Order dated 10.01.2019 in the matter of Petition under Section 86 (1)(b) and other provisions of the Electricity Act, 2003 for approval of bidding process, adoption of tariff of Municipal Waste based plant and approval of draft PPA |
10/01/2019 |
10/01/2020 |
|
Download (197.92 KB) |
|
|
Order dated 14.12.2018 in the matter of Approval of project specific tariff for generation and sale of electricity from part of the Petitioner’s 12MW Integrated Waste to Energy Power Plant Project based on Refuse Derived Fuel (RDF) at Ghazipur, Delhi |
14/12/2018 |
14/12/2018 |
|
Download (117.19 KB) |
|
|
Corrigendum dated 30.11.2018 in the matter of Notification of Laboratory for testing of tampered meter under Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017 |
30/11/2018 |
30/11/2018 |
|
Download (134.14 KB) |
|
|
Order dated 26.11.2018 in the matter of Scheme for implementation of DSM based Energy Efficient Air-Conditioner program in UT of Delhi under Demand side management programme |
26/11/2018 |
26/11/2018 |
|
Download (196.67 KB) |
|
|
Corrigendum dated 30.11.2018 in the matter of Notification of Laboratory for testing of tampered meter under Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017 |
23/11/2018 |
23/11/2018 |
|
Download (134.14 KB) |
|
|
Order dated 02.11.2018 in the matter of Approval of project specific tariff for generation and sale of electricity from part of the Petitioner’s 12MW Integrated Waste to Energy Power Plant Project based on Refuse Derived Fuel (RDF) at Ghazipur, Delhi |
02/11/2018 |
02/11/2018 |
|
Download (275.82 KB) |
|
|
Order dated 02.11.2018 in the matter of Petition under Section 86 (1)(b) and other provisions of the Electricity Act, 2003 for approval of bidding process, adoption of tariff of Municipal Waste based plant and approval of draft PPA |
02/11/2018 |
02/11/2018 |
|
Download (217.43 KB) |
|
|
Order dated 24.09.2018 in the matter of Delhi Electricity Supply Code and Performance Standards (Removal of Difficulty) Third Order, 2018 (Disconnection or Reconnection in case of sealing of premises) |
24/09/2018 |
24/09/2018 |
|
Download (229.83 KB) |
|
|
Order dated 24.09.2018 in the matter of Review Petition seeking review of the order dated 28.03.2018, passed by the Commission in Petition no. 67 of 2017 |
24/09/2018 |
24/09/2018 |
|
Download (318.97 KB) |
|
|
Order dated 18.09.2018 in the matter of Determination of Open Access Charges and related matters |