|
Report |
|
Need for the Meter Testing Drive |
-
Keeping in view the large number of complaints that
were being received regarding the electronic meters which have
been installed in the NCT of Delhi, the Delhi Electricity
Regulatory Commission (DERC) decided to undertake a limited
meter testing drive in order to allay the fears in the minds
of the public regarding electronic meters. This meter testing
drive was initiated by this Commission from the 1st
of October, 2005 and it concluded on the 10th of
January, 2006.
-
Earlier to this, there have been several other meter
testing drives which include testing of meters by this
Commission in 2003 wherein random samples were picked up from
the godowns of Distribution Companies. Subsequently, the
Distribution Companies also conducted there own meter testing
drives in July/ August 2004 wherein the services of the
Central Power Research Institute, an autonomous body of the
Ministry of Power, Government of India, was taken as an
independent third party. Separately, the Government of NCT of
Delhi had also conducted a meter testing drive in October/
November 2005 under the supervision of the Sub-Divisional
Magistrates.

|
|
DERC’s meter testing team
|
-
In the latest initiative by this Commission which
took place during the period 1st of October 2005 to
10th January 2006, the Central Power Research
Institute (CPRI), an accredited laboratory of NABL and the
Bureau of Indian Standards (BIS) were also associated. The
meter testing team thus comprised of officials of the DERC and
the officials of the BIS and the CPRI. Officials of the
Distribution Companies concerned were also a part of the team
since without the presence of the Distribution Companies, the
testing drive could not have been conducted. The list of the
officials from the DERC, the BIS and the CPRI who took part in
this meter testing drive is given at
Annexure – I.
-
It would be pertinent to add that the BIS was
associated with this drive since BIS is the government agency
which has the mandate for laying down standards for electronic
meters. Both domestic and foreign manufacturers have to get a
BIS certificate before they can release their electronic
meters in Indian markets. The choice of CPRI was arrived at
after the DERC floated a limited tender, seeking the services
of a NABL accredited laboratory in the public sector having
the requisite experience for on-site meter testing. The
testing of meters was conducted using CPRI’s own test
equipment.

|
|
Public Notice for meter testing |
-
The Delhi Electricity Regulatory Commission issued a public
notice on 5.9.2005 in seven leading newspapers comprising of English,
Hindi, Urdu and Punjabi newspapers, inviting requests from the public for
testing of meters. A copy of the public notice is given at
Annexure – II.
The drive was restricted to single phase domestic electronic
meters only and the Residents Welfare Associations (RWAs) were
requested to forward the names of two consumers whose
electronic meters were suspected to be faulty. Though the
public notice had indicated that the complaints should be
routed through the RWAs, individual complaints which were
received in the Commission were also entertained. A total
number of 626 applications were received from the consumers in
the NCT of Delhi.
 |
|
Procedure of testing of meters |
-
The procedure adopted by the team for carrying
out of testing of meters is as follows:
-
Each meter
was tested for a minimum consumption of 1 kWH.
-
Only optical scanners were
used for counting the pulses.
-
Standard
reference load of 4-6 KW was used.
-
Meter
testing report was generated on site itself and signed by all
members of the team as well as the consumer. A copy handed over to the consumer at the site. A sample copy is
enclosed at
Annexure – III.
-
For testing of meters,
a standard reference meter of
0.2 Class accuracy was used. The reference meter was Zera
make, imported from Germany and owned by the Central Power
Research Institute (CPRI), Bangalore. The reference meter was
calibrated by the CPRI in the month of June, 2005.
 |
|
Results of meter testing drive |
-
A total of 536 meters were tested during the
drive. The results of the drive are as tabulated below:
Table –1
|
Company |
Total
Applications
received
|
Total
meters
tested
|
Slow |
Meters found with errors between +/- 3% |
Fast |
Common
Neutral
problems
|
BRPL
|
330 |
266 |
0 |
263 |
3 |
24 |
|
BYPL |
172 |
157 |
0 |
157 |
0 |
50 |
|
NDPL |
124 |
113 |
0 |
112 |
1 |
22 |
|
Total |
626 |
536 |
0 |
532 |
4 |
96 |
Note: Out of 532 meters found within +/- 3%, 479 meters were
found to be within +/- 1%
-
The break-up of the meters not tested and reasons thereof are
given below:
Table -2
|
S. No. |
Reason |
Total |
BRPL |
BYPL |
NDPL |
|
1. |
Meter defective |
11 |
7 |
1 |
3 |
|
2. |
Mechanical meter |
6 |
4 |
- |
2 |
|
3. |
Consumer not interested |
29 |
20 |
6 |
3 |
|
4. |
Meter replaced before testing |
8 |
7 |
- |
1 |
|
5. |
Letter returned |
12 |
9 |
3 |
- |
|
6. |
Premises locked |
9 |
6 |
3 |
- |
|
7. |
Others |
15 |
11 |
2 |
2 |
|
|
Total |
90 |
64 |
15 |
11 |

|
|
Analyses of test results |
-
While the statistics of the meters tested are
already indicated in Table-1, it is clear from the results
that the electronic meters which have been installed by the
Distribution Companies are functioning well within the
stipulated limits under the Indian Electricity Rules, 1956. In
fact, most of the meters are functioning between +/- 1%
whereas the limits setup by the Indian Electricity Rules 1956
is between +/- 3%. Similar results were also arrived at by the
earlier test-drives conducted by the DERC/ the GNCTD/ the
Discoms. What has been observed, however, is that there is a
problem of bunching of neutral wires in many cases which may
lead to aberrations in recording of electricity consumption?
This problem was especially noticed in the case of
multi-storied houses, DDA flats, Consumer Group Housing
Societies etc. Though the problem of neutral wiring has been
observed in as many as 18% of the meters tested, it would not
be appropriate to extend this ratio to the entire city of
Delhi since the meters tested were not a representative
sample. It has to be borne in mind that it is only those
consumers who felt that their meters were faulty had
approached this Commission for testing and, therefore, this
ratio would naturally be relatively high.
-
The problem of neutral wires arises because of
faulty wiring in the consumer’s premises and this has to be
rectified by the consumers themselves. Whether a consumer is
having a faulty wiring or not can very easily be determined by
observing the Earth Leakage indicator in the electronic meter.
In case of any fault, the LED for Earth Leakage starts
glowing. This issue was highlighted by the Commission in its
advertisement “Do’s and Don’ts for change of meter/ meter
testing”, published in eight newspapers on the 1st
of August 2005. A copy of the advertisement is given in
Annexure IV.
There is no doubt, however, that the Distribution Company
should have advised the consumers of this potential problem
while moving from mechanical to electronic meters. The DERC
has given certain directions to the Distribution Companies in
this regard which is highlighted below.

|
|
Follow-up action taken by DERC |
-
The problem of neutral wires, however, is an issue
which clearly needs to be addressed and the Commission had
held discussions with the Distribution Companies in the month
of November 2005 and directions were issued to them on 28th
of November 2005 which included the following:
-
The Discom will immediately give a public advertisement,
drawing the attention of consumers of the potential
earth-leakage/ neutral wire problem which could be determined
by observing the meter itself. Such of those consumers who
observe Earth Leakage/Neutral Wire problem shall be advised to
report the matter to the concerned Discom for further advice
in the matter.
-
The meter readers of the Discoms will advise the
consumers wherever there are indications in the meter that
there could be an earth leakage/neutral problem. The meter
reader will simultaneously inform the Discom also and the
Discom will send their staff to ascertain if it is a problem
of earth-leakage or neutral wire. The consumer would be
suitably apprised of the remedial measures. This exercise
would be completed within the next two months.
-
The Discom will simultaneously conduct an analysis of
their billing module to segregate those meters where increase
in consumption has been recorded to the extent of 50% or more
after installation of electronic meters. Such meters would
immediately be checked for internal wiring problem so that the
consumers can be suitably apprised. This exercise shall be
further extended to consumption in excess of 30% also in due
course.
-
For rectification of the problem of neutral
wire/earth-leakage, the consumers may take the services of
electricians identified by the Discoms or employ their own
electricians for this purpose.

|
|
Action taken by the Distribution Companies |
-
The Commission had reviewed the matter in a meeting with the
Distribution Companies, held on 13.1.2006, wherein the
following feedback was given by the Distribution Companies:
-
Public
advertisements/ pamphlets have been issued by the Distribution Companies,
cautioning consumers of the problem of neutral wires and
requesting them to check the LED lights of their electronic
meters. Copies of such advertisements/ pamphlets are at
Annexure V
and
VI
respectively.
-
In the case
of BSES companies, the issue of neutral wires has been
highlighted in the electricity bills of consumers (copy at
Annexure VII).
The NDPL has addressed individual letters to all consumers
whose meters were changed to electronic meters requesting them
to check their meters for any indication of earth leakage
(copy at
Annexure VIII).
-
Meter
readers of all the three Distribution Companies are checking
each individual meter for potential neutral problem and it
would take about two months to identify all such consumers.
This exercise would thus be completed by about mid-March 2006.
-
Electricians have been trained by the Distribution Companies
who can advise the consumers on the presence of neutral
wire problem and its rectification.
 |
|
Annexure I
Composition of Team |
|
A
team of representatives of Commission, CPRI and BIS was
constituted to test the meters. Each testing team included one
representative from each of the organisations. Representative
of the respective licensee was also associated for witnessing
the test.
|
DERC: |
Shri Ajay K. Kaundal, Dy. Director (T &D)
Shri Anish Garg, Dy. Director (T &D)
Shri S. K. Sinha, Dy. Director (Tariff-Engg.)
|
|
BIS: |
Shri Ghanshyam Jha, Director
Shri S. K. Kanogia, Joint Director
Smt. Manju Gupta, Joint Director
Shri Rajiv Sharma, Joint Director
Shri K. R. Ahir, Dy. Director
Shri Jitender Kumar, Asstt. Director
Shri Ram Singh, Asstt. Director
Shri A. Kannappar, Asstt. Director
|
|
CPRI: |
Shri M. Kudloor, Engg. Officer
Shri P. Kalippan, Engg. Officer
Shri V. Suresh, Engg. Officer
Shri S. G. Dugad, Engg. Officer
Shri R. Hari, Engg. Officer
Shri V. Shiva Kumar, Engg. Officer
Shri B. L. Jayadev, Engg. Asstt.
Shri Shankara Murthy, Engg. Asstt.
Shri K. Lesly, Engineer |

|
|
Annexure I
Composition of Team |
|
Public Notice Dated
5th September 2005
DELHI
ELECTRICITY REGULATORY COMMISSION
(A statutory body of Govt. of NCT of
Delhi)
Viniyamak Bhawan,
Shivalik, Malviya
Nagar,
New Delhi – 110 017 PUBLIC NOTICE

The Delhi Electricity
Regulatory Commission (DERC), a statutory body set-up by the
Government of NCT of Delhi, announces a Meter Testing Drive
for Domestic Electronic Meters with the association of
the Bureau of Indian Standards (BIS) and the Central Power
Research Institute (CPRI), an autonomous body under the
Ministry of Power, Government of India. This drive would be
for a period of three months, i.e. from 1st
October, 2005 to 31st December, 2005.
-
This is a
one-time drive by the Commission and the salient features are
as follows:
-
This drive is limited to domestic electronic meters
only.
-
All Resident Welfare Associations (RWAs) in the NCT of Delhi
who are being served either by NDPL or BSES may forward names
of two domestic consumers whose electronic meters are
suspected to be faulty. The names of the consumers may be
forwarded either by post or via e-mail (secyderc@nic.in) to
Shri V.J. Talwar, Director (Engg.), DERC along with the
following details:
a.
Address of the consumer
b.
Telephone no. of the consumer
c.
New K.No.
d.
Whether Single-phase or Three-phase meter
e.
Name of the Licensee: whether NDPL/BSES Yamuna Power
Ltd./BSES Rajdhani Power Ltd.
-
During the three months period, i.e. 1st October, 2005 – 31st
December, 2005, the Commission would be able to test
approximately 500 electronic meters. In case the number of
consumers who wish to get their meters tested exceeds 500, a
computer generated sample of 500 meters would be drawn up by
the Commission.
-
The meter testing team will include officials from the DERC,
the BIS and CPRI. The team will inform the consumers of the
date of their visit at least three days in advance.
Representatives of the RWAs are requested to be present when
the test is conducted.
-
All the RWAs are requested to forward the names of the two
domestic consumers selected to the Commission, latest by 19th
September, 2005.
-
The test report would be given to the consumer immediately
after the completion of the test at site.
-
The entire expenditure for this drive shall be met by the
Commission.
-
For any further
clarification, Shri V.J. Talwar, Director (Engg.), DERC may be
contacted at telephone No.26673613.
Secretary, DERC
 |
|
Annexure III
Sample Meter Testing Report
handed over to the Consumer at the Site |
|
Delhi Electricity
Regulatory Commission
Viniyamak
Bhawan, C-Block, Shivalik, Malviya Nagar, New Delhi-110017
Meter Testing
Report
Date : 19.12.2005
|
Consumer Particulars |
Test Parameters
|
Revolution/Pulses Test |
|
K. No.: 35300550002Q |
Phase Current (A): 19.55 |
Meter Constant: 3200 |
|
Meter No. : 0103278872 |
Neutral Current (A): |
Reading Before Test: 11800 |
|
District: Shakti Nagar |
Phase – Neutral Voltage (V): 195 |
Reading After Test: 11801 |
|
Sanctioned Load (KW): 0.25 |
|
No. of pulses taken: 3200 |
|
Consumer’s Name: Smt Anar Devi |
|
Energy recorded by meter: 1000
Wh |
|
Address: H No. – A-58, Shastri Nagar,
Delhi-52
Phone No.: 23645981
|
Load (kW): 3.86
Power Factor : 1
Frequency (Hz): 48.7
|
Energy recorded by Reference
meter:
999.0 Wh |
|
Meter Particulars |
Instant Parameters |
Error : + 0.10 % |
|
Size/Rating: 10 – 60 A, Class – I |
Phase Current(A): 12.87 |
|
|
Meter Type: Single Phase |
Neutral Current (A): 14.29 |
Status of LED |
|
Meter Make: L & T |
Phase – Neutral Voltage(V): 198 |
Phase : OK |
|
Status of Seals |
Neutral--Earth Voltage (V) : 23 |
REV : Off |
|
Meter Seals: OK |
Phase-Earth Voltage (V) : 202 |
EL : Intermittently On |
|
Terminal Box Seals: OK |
|
Pulse : OK |
|
|
Power factor: 0.74
Temperature (oC): 20
|
Time taken: 15 min 51 sec |
Result : Consumer Meter recorded 0.10 % more
consumption.
It is to
certify that the testing has been carried out as per the
procedure prescribed by the Commission. An external load of
3.86 kW was used for testing for 1 kWh. The testing was
carried out by using optical scanner for counting the pulses.
Earthing from pole to meter is not proper. NDPL has been
advised to rectify the same.
Difference
between phase current and neutral current has been observed.
There could be neutral mixing with the other meter in the
premises. Further, earthing is also not available in consumer
premises. The consumer has been advised to get both of these
faults rectified. Before entering the premises Identity card
was shown and visiting card handed over to the consumer.
 |
|
Annexure IV
Public Notice - Dos and Don'ts
for Change of Meter / Meter Testing |
|

PUBLIC NOTICE

Meter Testing/ Changing is to be carried out by Licensee’s
officials only. Consumers are advised to insist for production
of Identity Card and Visiting Card of the Licensee’s official
heading the team before allowing them to enter the premises.
Entry to premises may be refused if team is not accompanied by
Licensee’s official or if such official fails to produce both
the Identity Card and Visiting Card.
APPROVED PROCEDURE FOR CHANGE OF METER
-
Meter change shall be carried out in the presence of
Registered Consumer or current occupant of the premises.
-
The meter changing team shall bring all the required material,
including wires, insulation tape, nuts and bolts, etc. and
consumer shall not be asked to supply any material.
-
Meter changing team shall ensure that all connections to meter
are properly done and there are no loose/bare wires.
-
Team shall also ensure that meter and terminal box are
properly sealed after installation.
-
The consumer should ensure that a copy of the meter change
report is handed over to him after change of meter.
-
Consumer should cross check his old and new meter numbers,
final reading of the old meter and the initial reading of the
new meter before signing the report
-
After installation of new meter, if it is observed that ‘E/L’
(Earth Leakage) LED is emitting light (indicating some leakage
in the internal wiring of the consumer), the consumer shall be
advised by the Licensee to get his wiring checked to remove
such leakage.
APPROVED PROCEDURE FOR METER TESTING
-
The meter shall be tested for at least 1 kWh
-
Optical scanner shall be used for counting of
pulses/revolutions
-
The testing team should carry external load of appropriate
rating of 1 kW to 3 kW.
-
Approximate time required for meter testing for 1 kWh is as
under
|
External load in kW* |
Approx. time required |
|
Less than 1 kW |
More than 1 hour |
|
Between 1 – 2 kW |
30 min. to 1 hour |
|
Between 2 – 3 kW |
20 min. to 30 min. |
Licensee’s testing kit would indicate the load used during the
test.
The consumer may record the time consumed
during testing while signing Meter Testing Report. The
consumer may also verify all the entries made in the report
before signing it.
In case of all meter related
complaints, the Licensees may be contacted at the following
telephone numbers
·
BSES Rajdhani
Power Limited -
39999733
·
BSES Yamuna Power
Limited -
39999733
·
North Delhi Power
Limited -
55111912

This notice has been issued in public interest for the
knowledge of consumers in the NCT of Delhi.
Secretary, DERC
 |
|
Annexure V
Public Advertisements issued by
BSES (BRPL and BYPL) Cautioning Consumers to check LED lights
of their Electronic Meters |
|

 |
|

 |
|

 |
|
Annexure VI Pamphlets issued by NDPL Cautioning Consumers
to check LED lights of their Electronic Meters |
|

 |
|
Annexure VII Electricity Bill where Neutral
Wires Issue has been Highlighted in Case of BSES Companies |
|

 |
|
Annexure VIII
NDPL Letters to Consumers
Requesting to Check Meters for any Indication of Earth Leakage |

NOTICE TO CONSUMERS
Metering
NDPL is committed to continuously improve its services
associated with electricity distribution, while ensuring
supply at competitive costs and recovery of dues from all
concerned. This is possible by ensuring that all units of
electricity bought by NDPL from the grid are properly
accounted for and the units consumed at any premises are
recovered from the consumer concerned. As such, NDPL has been
migrating its metering system to state of the art electronic
meters, which have significant tamper-proof features. Also,
NDPL is now able to reconcile bulk energy transfers up to the
point nearest to your premises, which is a Feeder /
Distribution Transformer. We are now in a position to
ascertain the gap between Energy provided by NDPL (into a
Feeder / Distribution Transformer) and that accounted by
aggregation of meter readings of consumers connected to such
feeders / transformer. This gap reflects the
un-accounted/un-metered consumption at the consumer-end.
The Hon'ble High Court of Delhi has vide its order dated
14-12-2005 in writ petition WP(C) No. 12328/2005 recently
upheld that a Discom has the right to change, replace the
existing meter with Electronic meter without the need to check
the existing meters accuracy or status.
Wiring
It is vital from safety and accurate meter reading point of
view that the internal wiring inside consumer premises is safe
and correct. It is noteworthy that the Indian Electricity
Rules, 1956 read with the National Electrical Code and the
National Building Code issued by the Bureau of Indian
Standards -
-
Oblige the consumers to maintain the internal
wiring in good and correct condition at all times.
-
Require that no electrical installation work
(including additions, alternations, repairs and adjustments to
existing installation) be carried out upon the premises on
behalf of any consumer/owner except by qualified personnel
-other than replacements of lamps, fans, fuses, switches, low
voltage domestic appliances and fitting that do not alter the
capacity and the character of the installations.
-
Mandate that Interconnection of phases or
neutrals of consumer loads must be avoided between two or more
metered connections (read with IS 13779, Amendment 3 of
December 2004).
If you are in an independent house with one independent
metered connection you are not likely to encounter intermixing
of wires. However, if you are in cluster of premises, you need
to check and ensure that your internal wiring is independent
of wiring of other metered premises.
All consumers where new Electronic Meters have already been
installed are hereby advised to get their wiring checked for
Earth Leakage and Intermixing of wiring (phase, neutral)
between two or more metered connections.
NDPL has trained such of the neighborhood electricians who
volunteered themselves and the list, contact details of such
electricians is placed on NDPL web site or can be obtained
from its consumer care centers.
For all future installation of new electronic meters, NDPL
shall check the wiring status for any intermixing, earth
leakage and connected load and inform consumers about any need
to get a problem rectified as on the date of checking.
With a view to protecting the internal wiring within consumer
premises as also for safety, NDPL recommends the use of Earth
Leakage Circuit Breakers (ELCB) as main switch immediately
after the Meter. This is designed to protect internal wiring
as also secure against any Earth Leakage or Wiring errors,
wrong interconnections, leakages that may arise within
consumer premises. Please note that the use of ELCB' s is also
mandated by law for premises with loads equal to or above 5
KW.
For any further clarifications consumers are encouraged to
contact our commercial call center at 55111912 between 9.00 am
to 9.00 pm on all days or visit our consumer care centers.
NDPL -Hum Milkar
Ek Ujwal Kal Banayeg
 |